- EOSS is well-known and respected in the UAE marketplace as both a professional and reputable service provider. EOSS is also considered an unparalleled leader in the field of structured cabling and patch cord provision in the UAE.Following are relevant ongoing and completed projects
Project Name : Dubai International Airport Expansion Phase 2- Concourse 3 (AX 140)
Location : Dubai
Client : Thales International
Date : 2011-2012
Description : Installation and Commissioning of Structured Cabling Network and 48V DC System:
- Fiber Optic System: Fiber Optic Cable Installation of more than 80 Kms (Including 96, 36,24,18,12,6 and 2 Cores FO Cable. Fiber Optic cable Termination, testing and commissioning of more than 70,000 cores(The biggest Fiber to Desk Installation)
- Equipment Installation: Installation of Control Room Equipments and FO Outlet and FTTO Switches
- Rack Installation: Installation and arrangement of 96 Cabinets of size between 42U and 9U
- Copper Cabling: Copper Cable Installation of 58 Kms (100 Pair, 50 Pair, 4 Pair and Cat5e, Cat 6). Copper Cable termination and testing of more than 5500 Pairs
- Power Cabling: Power Cable Installation 160 Kms, Power Cable Testing & Installation of 5942, Power Termination of 6000 FTTO Switches
Project Name : Dubai Metro
Location : Dubai
Client : Thales International
Date : 2009 – 2011
Description : Installation and Commissioning of Low Voltage Systems including the following systems(CCTV system, IAS system, TDS system, TN-ECB system PAS-PIS system) in Dubai Metro Red line.
Each system consisting of the following:
- CCTV – installation of 650 CCTV cameras, splicing, installation and termination of FO/UTP cable in converter box, laying of 38,000 meters of 4 core fiber optic cable, laying of 32,200 meters of UTP CAT6 cable and laying of 38,000 meters of power cable
- IAS – laying of 39,490 meters of power cable, UTP CAT6 cable, Belden cable and armoured copper pair cable
- TDS – installation of 8 Sub master clock and 40 indoor digital clock, laying and termination of 3,200 meters of power cable and signal cable
- TN-ECB – installation of 36 ECB and 233 BLS telephone on wall/pole, laying of 31,195 meters of COM cable
- PAS-PIS – installation of 4,013 loudspeakers, 100 ambient noise sensor, 84 LCD displays, laying and termination of 71,583 meters of power cables and fiber optic cables
- Fixing and Installation of 160 BBR access point boxes and related 3 meter pole structures including termination and 60 NBR poles including structure and 25 CCTV pole structures along wayside and stations in Dubai Metro Red line
Installation and Commissioning of Low Voltage Systems including the following systems(CCTV system, IAS system, TDS system, TN-ECB system PAS system, FON system) for both Jumeirah and Rashidiya carparks
Each system consisting of the following:
- CCTV – installation of 998 outdoor IP cameras, 3,992 terminations of fiber at ODF, laying of 517,463 meters of fiber optic cable, SSTP Cat6 cable and power cable
- IAS – installation of 57 Door control module, proximity card reader and laying of 23,095 meters of power cable, SSTP Cat6 ethernet cable and Belden cable
- TDS – installation of 2 central master clock and digital clock, laying and termination of 100 meters GPS antenna cable, laying and termination of 333 meters of power cable
- TN-ECB – installation of 59 ECB, laying of 23,802 meters of twisted pair cable, termination of 67 telephone cables at socket
- PAS – installation of 3,086 loudspeakers, 87 ambient noise sensors, laying and termination of 137,284 meters of power cables
- FON – laying of 1,100 meters of 24 core fiber optic cable, and terminations of 96 fiber at ODF
Project Name : Borouge II Expansion
Location : Ruwais
Client : Thales International
Date : 2009 – Ongoing
Description : Supply and Installation of Structured Cabling System in Borouge II expansion,Survey, Cable pulling, Labeling, Termination and Testing of the Outside Plant Cabling System, Installation of Low voltage system including the following systems (PABX-Hot Line facilities, Public Address system, CCTV system, Master Clock system)
Our job consists of:
- PABX-Hot Line Facilities – pulling of 750 meters of 20p telephone cable, installation of 11 Analogue telephones, laying of 9,600 meters telephone cable and power cable
- Public Address – installation of 17 central equipments, pulling of 5,080 meters cable for loudspeakers, laying of 34,671 meters of 2pair telephone cable, fixation of 488 loudspeakers
- CCTV – pulling of 8,800 meters of fiber optic cable and power cable, fixation, installation and testing of 9 CCTV cameras
- OPC – pulling of 43,868 meters of 24 core fiber optic cable with testing and pulling of 7,050 meters of 12 core fiber optic cable and drum testing
Project Name : Building Material City
Location : Abu Dhabi
Client : Toledo
Date : January 2010 – Ongoing
Description :Installation & Termination of Low Voltage systems – Fire Alarm systems, Building Management System, Access control system & CCTV systems
In Shopping mall
- Fire Alarm: Cable installation of over 27 Kms FP200 Cable, device fixing and termination of smoke detectors (700), break glass (50) and control relay modules
- BMS: Cable installation over 263 Kms of 1.5mm Signal wire, device termination of dampers, FCU controllers, etc.)
- Access control: Cable installation of over 17 Kms of Belden cables, device fixing and termination of card readers, door contacts, access intelligent controllers
- CCTV: Cable installation of over 120 Kms of RG6 Cable, device fixing and termination of indoor dome cameras
In Tower 16 & 17
- Fixing, termination and testing of addressable modules in Emergency light (over 1200 + lights)
- CCTV Rack termination and testing of 51 Cameras in Tower 16
Project Name : Officers Club
Location : Abu Dhabi
Client : Al Fahad Smart Systems
Date : April 2010- August 2010
Description : Installation, termination, testing, labeling and commissioning of 858 indoor/outdoor IP Camera System (DC system)
Supply and Installation of 79 Intermediate Distribution Frames, 2 Optical Distribution frame along with 1 Main Distribution Frame
Installation of 20 kilometers of fiber optic cable and 60 kilometers of UTP Cat 6 Cable
- In West Wing
Supply, installation of 18 Intermediate Distribution Frame
Installation, initial focusing and configuration of 142 IP Cameras
- In East Wing
Supply, installation of 18 Intermediate Distribution Frame
Installation, initial focusing and configuration of 142 IP Cameras
- Main Building & Basement
Supply, installation of 43 Intermediate Distribution Frame
Installation, initial focusing and configuration of 611 IP Cameras